Structural Engineer Brief
Bridge House, Unit 1, 26 Ducie Street, Manchester. Cat B office fitout requiring structural works to existing concrete-frame building.
1. Existing Building
Two-storey commercial building. Ground Floor and Lower Ground Floor connected by an existing metal staircase at the rear (north). This is a lightweight steel staircase that can be unbolted and removed. The slab opening will be infilled. The existing south entrance has concrete steps that require careful demolition. New vertical circulation (staircase and DDA lift) will be formed at the front (south) of the building.
Existing Staircase (To Be Removed)
North (rear) of building
Metal staircase. Lightweight steel construction, bolted to slab. Simple removal.
Ground Floor to Lower Ground Floor
3000mm x 4000mm
The Green, MLP Design. GF: 1171-FP-01 Rev A (1:200 @ A4). LGF: 1170-FP-01 Rev A (1:200 @ A4). Both dated 11/06/2019.
Steel/metal frame. No embedded reinforcement in staircase itself. Bolted connections to existing concrete slab at GF and LGF levels.
Unbolt and remove metal staircase. Infill slab opening with RC slab to match surrounding floor level.
Key Dimensions
~4900mm x 5170mm (264 sqft)
~5700mm x 4690mm (261 sqft)
3000mm x 4000mm
4725mm
3675mm
1050mm
2. Scope of Structural Works
Sequence: survey existing structure, remove rear metal staircase (unbolt), install temporary propping, demolish concrete south entrance steps, infill rear slab opening, cut new openings at front, install edge trimmers, excavate lift pit. All to SE design.
New Slab Openings Required
2400mm (W) x 4200mm (D)
2700mm x 4500mm (including 150mm enclosure walls)
One combined opening. The GF straight flight (6R, 1200mm x 1500mm) sits within the LGF stairwell void above the LGF dog-leg below. No separate GF opening needed.
1500mm (W) x 1700mm (D)
1800mm x 2000mm (including 150mm shaft walls)
Separate opening adjacent to stairwell. Full height from LGF pit to GF headroom zone.
1500mm x 1700mm x 1100mm deep
1800mm x 2000mm external (pit walls)
Below LGF slab level. Waterproof tanking required. Sump pump if below water table. Base slab to SE design.
3. Position Structural Zones
Drag zones to position. Click a zone in the legend to edit its dimensions.

4. Position Structural Zones on MLP Plans
Drag zones to position. Click a zone to edit dimensions. Hide zones per floor without affecting the other.

5. Building Measurements & Structural Dimensions
All measurements drawn on MLP Design floor plans. Toggle layers to show/hide perimeter walls, columns, and column grid spans. Zone dimensions from the placer above are the source of truth. All dimensions to be verified on site.

All dimensions measured from MLP Design floor plans (1:200 @ A4, 600 DPI, calibrated at 118.75 px/m). Column sizes approximate from plan. All dimensions in mm. Verify on site before works commence.
6. Structural Works Plans
New works overlaid on the existing Ground Floor plan. 1:50 at A1. Red = demolition. Blue = new stairwell. Green = new lift shaft.
Builder's Works Plan (All Structural Works)
Staircase Works Plan
Lift Works Plan
7. New Staircase Specification
New staircase at front (south) of building. Three flights serving LGF, Street Level, and GF.
LGF: U-shaped dog-leg. GF: straight flight. Both share street-level landing.
Flight 1a (west, 12R heading north) + intermediate landing + flight 1b (east, 9R heading south). Open well between flights.
Straight flight, 6 risers from street level landing up to GF, heading north.
175mm (Part K max 220mm)
250mm (Part K min 220mm)
600mm (target 550-700mm)
1200mm between handrails (Part K min 1000mm)
2000mm minimum (Part K)
3675mm (21 risers x 175mm)
1050mm (6 risers x 175mm)
4725mm (LGF to GF)
Steel or reinforced concrete
Both sides, 950mm height, brushed steel or brushed gold. Continuous across landings.
Polished concrete to match screed, or steel plate with anti-slip nosings
Contrasting anti-slip nosings to all treads (Part M / Part K)
FD30S self-closing fire doors at each level, 900mm clear opening
Maintained emergency lighting per Part B and BS 5266
2400mm (W) x 4200mm (D)
2700mm (W) x 4500mm (D) including 150mm enclosure walls
6. DDA Passenger Lift
New passenger lift adjacent to stairwell at front (south) of building. Three stops.
Schindler 3100 MRL (or equivalent)
Machine Room-Less passenger lift
400kg / 5-person
1.0 m/s
2 (LGF and GF). Street level is intermediate stop.
3 (Lower Ground Floor, Street Level, Ground Floor)
4725mm total. LGF to Street: 3675mm. Street to GF: 1050mm.
1100mm x 1400mm internal (DDA minimum)
Automatic sliding, stainless steel finish, 900mm clear opening
LGF and Street Level doors open south. GF door opens north (into building). Through-car at GF only.
3-phase 400V, 16A isolator, TPN MCB in main distribution board
EN 81-20, EN 81-50, Equality Act 2010, Part M
LED car lighting, ARD battery lowering, emergency intercom, overload sensor
Shaft Requirements
Blockwork or reinforced concrete walls, minimum 1-hour fire rating
1500mm x 1700mm internal. 150mm wall thickness.
1800mm x 2000mm overall (including walls)
Full height from LGF pit through street level to GF
1100mm depth. Waterproof tanking required. Sump pump if below water table.
3400mm above top landing (GF). Per EN 81-20.
Shaft ventilation per Part B and EN 81-20
Builder's work drawings required from lift manufacturer before construction
7. Required SE Deliverables
Structural engineering calculations, designs, and sign-offs required before site works can commence. All deliverables to be provided before Week 1 site start.
Survey existing slab openings (rear metal staircase opening, south entrance) and surrounding structure. Confirm slab thickness, reinforcement details, and condition. Identify load paths affected by works.
Propping design for slab openings and concrete entrance demolition. Method statement for safe removal sequence. Propping positions, loads, and duration. Note: rear staircase is metal (simple unbolt), but slab opening infill requires propping.
Calculations for rear slab opening infill (300mm RC, dowel connections), concrete south entrance step demolition, and load transfer during works.
Design for forming combined stairwell opening in GF slab. Edge trimming, trimmer beams, reinforcement around opening. This single opening serves both the LGF dog-leg and GF straight flight.
Design for forming lift shaft opening in GF slab adjacent to stairwell. Edge trimming, trimmer beams. Coordinate with lift manufacturer builder's work drawings.
Reinforced concrete pit below LGF slab. Base slab, pit walls, waterproof tanking specification. Ground investigation may be required.
New shaft walls (blockwork or RC), 150mm thick, 1-hour fire rating. Full height from pit to GF headroom zone. Shaft to support guide rail loads.
U-shaped dog-leg stairwell: steel or RC flights, intermediate landing at half-height, connection to existing structure. Enclosure walls 150mm, fire rated.
Connection details for new steel to existing structure. Pad stones, base plates, bolt specifications. New-to-existing interface details.
Calculations for any other new openings through existing concrete/masonry structure. Lintel schedules where required.
8. Programme
Indicative structural works programme. SE deliverables must be complete before Week 1.
SE calculations, propping design, and lift manufacturer builder's work drawings must all be received before Wk 1 site start. Asbestos survey required before demolition. Note: rear staircase is metal (simple unbolt and remove). South entrance steps are concrete (require breaking out).
9. Download Packs
Structural Engineer Pack
Complete pack for SE quotation. Includes the brief PDF (9 pages covering project overview, existing building, scope of works, slab openings, staircase and lift specifications, SE deliverables, programme, and information outstanding), plus all supporting drawings and existing building plans.
01 Existing Plans
MLP Design GF + LGF (1:200)
02 Testfit Plans
Incognito Stage 1 (1:100)
03 GA Plans
GF + LGF (PDF/SVG/DXF)
04 Staircase Drawings
Section, plan, schedule
05 Lift Drawings
Section, plan, schedule
06 Structural Works
Stair, lift, builder plans on GF
07 Builder's Works
Full scope, specs, dimensions
08 Key Dimensions
All openings, heights, sizes
Staircase Tender Pack
Drawing pack for staircase contractor quotation. Developed section, plan views, specification schedule, and structural works plan.
Structural Works Plan
1:50. New stairwell on existing GF plan. Opening dimensioned.
Section (Developed)
1:20. All three flights with break marks at direction changes.
Plans + Specification
1:25 plan views. Full spec: flights, demolition, fire, regs.
Builder's Works Pack
Full scope of works for builder quotation. Includes structural works plan showing all zones on existing floor plan.
Structural Works Plan
1:50. All works on GF plan: demolition (red), stairwell (blue), lift (green).
Scope Document
Demolition, making good, slab openings, lift pit, all specs.
Key Dimensions
All opening sizes, floor heights, staircase and lift dimensions.
Lift Company Tender Pack
Drawing pack for lift company quotation. Shaft section, shaft plans, specification schedule, and structural works plan.
Structural Works Plan
1:50. Lift shaft on existing GF plan. Shaft, car, pit dimensioned.
Shaft Section + Plans
1:20. Pit, floor levels, headroom, doors, car outline, walls.
Specification Schedule
Full spec: general, shaft, car, doors, electrical, programme.